Thursday 1 September 2016

Downpipes appear to have been installed yesterday 31.8.16.

Not sure whats next ?????

Wednesday 31 August 2016

Locked Up

Yesterday 30.8.2016 drove past to see that we have a front door. 

It looks like we are at lock up......



Tuesday 30 August 2016

Samples


Lounge Purchase  for family room, see layout to scale (below) - see purchases tab


How clever lol



Samples of Fabric for Lounge



Tiles for main areas - they are more rough feel than a smooth feel, it has small flecks of glitter like material which should give some good light off



Sample of texture of 'Rug' carpet purchase just to work out size to go under the 2 x lounges - this is way cheaper than any rugs you can buy in large sizes


This is a silver grey colour - hard to tell from photo

Photo Update



Garage


Front of house


Ensuite Toilet after waterproofing


Ensuite Vanity / Entry after waterproofing


Ensuite Shower after waterproofing


Rear of House looking towards Alfresco


So that white mark centre of photo is "The Boundary" with the site fence up makes the yard look so much smaller


Down the side of the house


Rear of House / 10,000l tank position


Front door / Entry hall


Main Bedroom


Entry to Main bedroom looking towards Ensuite shower


Entry to Main Bedroom left bedroom area / right WIR and Ensuite


Dining / Family Room looking towards Summer Room


Garage Roller door


From Corner of Kitchen looking towards Dining / Family / Hallway entrance


Corner of Kitchen towards Dining area


Kitchen area towards dining / entry / garage entry


Main Shower getting waterproofed


Main Bathroom


Family Room looking back towards Kitchen / Pantry / Garage Entry


Kitchen area with door out to Alfresco area


Bricks Cleaned


Bricks Cleaned


We have a post


Front Porch looking through house


Bricks done, roof done, gutters done, fascia done from across street

Update 30 August 2016

Tuesday Update

1. Site Supervisor advised should be at lock up this week.
2. Waterproofing complete 27.8.16
3. Gyprock finished and sanded 26.8.16
4. Garage roller door installed 26.8.16

Now that the walls are up you can really get a view of how the house size is. The frames don't give you any idea of how the house will feel. 

In recent weeks a few purchases have been made. 

1. Lounge suite for family room area.
2. Carpet
3. Bedhead and base


Decisions / Quotes have been received.

1. Tiles - Skheme
2. Retaining wall for OSD (onsite storm water detention)
3. Landscaping wall for side rear of house
4. Driveway





Monday 18 July 2016

Brickwork


Brickwork was started on 4 July 2016.








Update 18 July 2016


Since the last update, a lot of things have happened

1. Concrete pits for Onsite Water Detention were delivered - I was told by the plumber that they sent the wrong ones. The correct ones came and have been put in place.
2. Frames were delivered on 20.6.16
3. Frames were completed 22.6.16
4. Bricks delivery 29.6.16 - only 4 pallets
5. Bricks started on 4.7.16

Since the brickwork has started 2 weeks ago now. A few days the brickies have not worked due to 'rain' or they did not appear on site.

Today is a day full of sunshine - after the Harbour city was covered in fog.



Frames delivered and spread out

Frames delivered and spread out

There she is... And her name is....

The Summer Room... 

Kitchen looking into Family room

Family room looking back to Kitchen / Dining

Kitchen / Dining looking to Kitchen and Alfresco area

Main Bedroom looking to entry alcove, WIR and to the right the Ensuite